Your P&L says it was a good month. Your bank account says otherwise. Or the opposite happens: cash looks great, and then a job runs out of money right before the finish work.
A lot of the time, the gap comes from billing and work getting out of step. A work-in-progress schedule, usually just called a WIP schedule, is the report that shows you where that's happening. It sounds like something only big commercial GCs need. It isn't. If you run more than a couple of jobs at once, it's one of the most useful reports you can have.
Here's what it is, how to build one, and what I'd check each month.
What a WIP schedule shows
A WIP schedule is one row per open job. For each job it compares three things:
- What the job should earn in total (the contract amount, including approved change orders).
- How far along the job is (usually based on cost spent versus total estimated cost).
- How much you've billed so far.
From those, you can see whether you've billed more or less than the work you've actually done. That difference is the whole point of the report.
The basic math
The most common approach is cost-to-cost percent complete. Here's a hypothetical job to walk through it:
- Contract amount: $150,000
- Total estimated cost: $120,000
- Cost to date: $60,000
- Billed to date: $85,000
- Percent complete = cost to date ÷ total estimated cost = $60,000 ÷ $120,000 = 50%.
- Earned revenue = contract amount × percent complete = $150,000 × 50% = $75,000.
- Over or under billing = billed to date − earned revenue = $85,000 − $75,000 = $10,000 overbilled.
So on paper you've collected or invoiced $10,000 more than the work you've done. That's not automatically bad. It just means that money is really for work you still owe the customer.
If billed to date were $65,000 instead, you'd be $10,000 underbilled: you've done work you haven't invoiced yet.
Why over- and underbilling matter
Overbilling can make you feel richer than you are. Cash comes in early, it gets spent on other jobs or overhead, and then the last 20% of the work has to be paid for with money that's already gone. A little overbilling on purpose can help cash flow. A lot of it, across several jobs, is a warning sign.
Underbilling is usually money you could be collecting. It can mean pay apps are going out late, change orders haven't been billed, or the schedule of values doesn't match how the work is actually happening. It can also mean costs are running over and the job isn't as far along as the spending suggests. That's the one to look at closely.
Both can hide a bad estimate. If cost to date climbs faster than expected, percent complete jumps ahead of reality, and the report can make an over-budget job look underbilled. That's why the estimate needs regular updates (more on that below).
How to build one
You can start in a spreadsheet. The steps are the same either way.
- List every open job. One row each. Closed jobs come off once final billing and retainage are settled.
- Pull the contract amount, including approved change orders. Pending change orders stay out until they're approved, or go in a separate column so you can see them.
- Pull cost to date by job. This only works if bills, payroll, and materials are actually coded to the right job. If job costing is messy, fix that first. (We wrote about job costing for Utah contractors if you want a starting point.)
- Update the estimated total cost. Ask the PM or whoever runs the job: knowing what you know now, what will this job cost to finish? Cost to date plus cost to complete.
- Pull billed to date. Include retainage that's been billed but held. Retainage has its own tracking, which we covered in our retainage post.
- Calculate percent complete, earned revenue, and over/under billing for each row.
- Add estimated gross profit. Contract amount minus estimated total cost, and the margin percent. Compare it to the margin you bid.
The monthly checks I'd run
Once the schedule exists, the value comes from reviewing it every month. Here's what I'd check:
- Did any job's estimated margin drop since last month? That's your earliest warning that something is going sideways.
- Which jobs are underbilled, and why? Late pay app, unbilled change order, or cost overrun? Each one has a different fix.
- Is total overbilling across all jobs bigger than your cash on hand? If so, you're leaning on future work to pay for current work.
- Are there approved change orders that haven't made it into the contract amount? This is a common reason a job looks worse than it is.
- Does the estimate to complete still make sense? If nobody has updated it since the bid, the percent complete is probably off.
- Does cost to date match the books? Tie the schedule's total cost back to your job cost reports so you're not working from two different numbers.
If you're working with a CPA, ask how they want over- and underbillings handled on your financial statements. Bonding companies and lenders often look at WIP schedules too, so it's worth asking what they expect before you need it. How revenue gets recognized for tax purposes is a separate question, and that one belongs with your CPA.
Spreadsheet, QuickBooks, or Odoo?
A spreadsheet is a fine place to start. The weak spot is that someone has to copy numbers in by hand every month, and that's where errors creep in.
QuickBooks can give you job cost and billing data to feed the schedule, though many contractors still end up building the WIP itself in a spreadsheet.
In Odoo, each job can be a project tied to an analytic account, so bills, timesheets, and invoices land on the job as they're entered. That makes cost to date and billed to date much easier to pull. As a specialist Odoo partner, we can also build a WIP report or a few custom fields (like estimate to complete) right into the system so the schedule updates from live data instead of a monthly copy-paste. What that looks like depends on how your jobs and billing are set up, so it's worth talking through before building anything.
Whichever tool you use, the habit matters more than the software. Update the estimates, run the schedule, and look at the jobs that moved.
Where to start
If you've never had a WIP schedule, don't try to make it perfect. Pick your five biggest open jobs, fill in the columns above, and see what jumps out. Usually one or two jobs tell you something you didn't know.